The Matheson Avenue Bridge streetscape project for the City of Charlotte will provide improved connections between North Tryon Street and the LYNX Blue Line, the Cross Charlotte Trail, and the popular NoDa area. The project includes pedestrian, bicycle, and aesthetic improvements on Matheson Avenue from North Tryon Street to Jordan Place,
The project will reduce Matheson Avenue from four lanes to 2 lanes, allowing the construction of a two-way cycle track along the south side and sidewalk along the south and north sides of Matheson Avenue. A three-foot-wide curb will be installed between the cycle track and the roadway.
The Matheson Avenue Street Conversion project, part of the city’s bicycle program, will provide streetscape improvements along Matheson Avenue between Jordan Place and The Plaza. This 0.6-mile streetscape project includes
- 4,790 SY Bridge Deck Rehabilitation
- 277 CY of latex modified Concrete overlay.
- 400 LF of 6” Concrete Multi-Use Path
- 2,280 SY Sidewalk
- 2,810 LF of Metal Handrail
Anticipated Start Date is Mid July 2024
Contract Amount $12.8 Million
https://www.charlottenc.gov/Growth-and-Development/Projects/AIC/Matheson-Streetscape